Deep well notification: when it is needed and how to file it

A deep well notification is a water-law notification (zgłoszenie wodnoprawne) filed with Wody Polskie, but an ordinary well of up to 30 m for your own needs is exempt from it. A notification comes into play for a deeper borehole, or when the water serves more than your own household. It is filed before the works begin, and the works may start after 30 days if the authority raises no objection.
Legal position as at 16.11.2026.
When a deep well notification is needed
Everything depends on the depth, the volume abstracted and the purpose the water is used for. For an ordinary domestic well, the exemption under the Water Law Act (consolidated text Dz.U. 2026 poz. 1335) applies:
Constructing an intake up to 30 m deep for ordinary use of water, and abstraction averaging no more than 5 m³ per day for the needs of your own household or farm, are exempt from a water-law permit and notification (Articles 33 and 395 of the Water Law Act). These are separate conditions concerning the construction of the intake and the abstraction of water. A deeper borehole, or using the water beyond ordinary use, requires checking the correct procedure with Wody Polskie. The exemption does not remove location requirements, the protection of intakes or geological regulations.
We explain in full how to decide whether you need a water-law permit in the article on the deep well permit. Here we deal only with the notification. The table below shows how different situations relate to a notification.
| Situation | Water-law notification | Where to check |
|---|---|---|
| Intake up to 30 m, ordinary use, abstraction up to 5 m³ per day for your own needs | Not required, exemption under Article 395 points 5 and 7 | The article on the permit, the Wody Polskie water supervision office |
| Borehole deeper than 30 m | The correct procedure must be checked | The Wody Polskie water supervision office |
| Water for a business, beyond your own farm or household | Relying on ordinary use is usually not enough | The Wody Polskie water supervision office |
| Discharge of water from pumping tests of hydrogeological boreholes or from construction excavations | Falls among the activities listed in Article 394 section 1 point 8 | The Wody Polskie water supervision office |
Where both a permit and a notification are needed for the same project, Article 394 section 4 requires them to be handled in a single procedure ending in a permit. If you are planning an ordinary borehole, see also our offer for a 30 m deep well.
Where to file a water-law notification
A water-law notification goes to the Wody Polskie water supervision office, not to the district office (starostwo). Under Article 397 of the Water Law Act, it is filed with the office that has local jurisdiction or the nearest one. Wody Polskie state on their website (checked 16.11.2026) that the notification is sent by post or submitted at the office, and a form is available to download.
Geological regulations are a separate matter. In Article 3 point 2a, the Geological and Mining Law (Prawo geologiczne i górnicze) excludes the application of the Act (and so also the obligation to prepare documentation and a project) to boreholes up to 30 m for intakes of up to 5 m³ per day, outside mining areas for medicinal waters and brines. A deeper borehole may bring geological requirements, so there is no single rule for every well.
What the notification contains and which attachments to include
The scope of the notification is set out in Article 421 and the attachments in Article 422 of the Water Law Act. Prepare:
- the identification of the establishment, that is, your details with an address,
- the purpose of the works and the legal status of the property,
- a description of the works, their parameters and the conditions of execution,
- the location: cadastral district, plot numbers and coordinates,
- the planned start date of the works.
The notification must be accompanied by a site and elevation map from the national geodetic and cartographic resource, and by sketches or drawings. Where it applies to your plot, you also need an extract and map extract from the local spatial plan or a development conditions decision, the consent of the owner of the water installation, and the confirmation of the notification referred to in Article 118 of the Nature Conservation Act. You will find the complete list of documents to gather in one place in the Help Centre: documents and offices in the Help Centre.
Notification step by step
The sequence of actions is simple, but all the steps must take place before the works begin.
- Check whether your well falls within the exemption. If it does, a water-law notification is not needed.
- Gather the data on the plot and the planned intake, together with a map from the geodetic resource.
- Fill in the notification form from Wody Polskie and add the attachments.
- Pay the fee for accepting the notification and attach the confirmation.
- File the notification with the water supervision office before the intended start date of the works.
- Wait 30 days and check with the office that there is no decision of objection. On request, the office issues a certificate that no objection was raised.
Acceptance of a water-law notification comes before the notification of construction or building works (Article 388 section 3). The enclosure of a groundwater intake does not require a building permit or a building notification under Article 29 section 2 point 25 of the Construction Law. This does not apply to other work around the well.
Deadlines and the fee for a water-law notification
The notification is made before the intended start date of the works. The deadlines in Article 423 run from that moment.
| What | Deadline | Basis |
|---|---|---|
| Starting works without objection | after 30 days from delivery of the notification | Article 423 section 2 |
| Request to supplement the notification | suspends the 30 days | Article 423 section 7 |
| Failure to supplement | ends with an objection | Article 423 section 4 |
| Appeal against a decision of objection | 14 days | Wody Polskie website |
| Acceptance of the notification | may take place before the 30 days have passed | Article 423 section 10 |
| Notification after 3 years from the planned date | becomes void | Article 423 section 3 |
Wody Polskie advise phoning the supervision office once the deadline has passed, because an objection is effective as soon as it is posted. The notification also does not release you from the approvals and decisions required by separate regulations (Article 423 section 2), and the authority may set requirements for the conditions of execution (Article 424).
According to Wody Polskie, the fee for accepting a notification is PLN 132.33 (checked 16.11.2026). Article 398 section 2 gives a lower base rate, but the current one is announced by the minister, so check the amount on the supervision office’s website before paying. A power of attorney costs an additional PLN 17 in stamp duty, with exceptions for close family.
Legalisation, distances and penalties
A well built without a required permit or notification can be legalised with Wody Polskie. We describe this separately in the article on legalising a well, together with the penalties and the amnesty for intakes built before 18.08.2026.
Distances from the boundary, septic tank and buildings do not follow from a water-law notification. The previous regulation on technical conditions ceased to have effect in September 2026 and the new one has not yet been published, so we agree the distances with the designer and the district office, relying on earlier practice and draft provisions. The details are in the articles on well distances from the boundary and buildings and distances, version 2. You will find a general overview of the subject in the guide to a private water source.
Frequently asked questions
Do you need to notify a well of up to 30 m?
No, if it is ordinary use of water: an intake up to 30 m deep and abstraction averaging up to 5 m³ per day for the needs of your own household or farm are exempt from a water-law permit and notification (Articles 33 and 395 of the Water Law Act). The exemption does not remove location requirements or geological regulations.
When do you need to notify a deep well?
When the borehole is deeper than 30 m, the water serves a business, or the project falls among the activities in Article 394 of the Water Law Act, for example discharging water from pumping tests. The correct procedure is confirmed by the Wody Polskie water supervision office.
Which wells do not need to be notified?
Wells of up to 30 m from which abstraction does not exceed an annual average of 5 m³ per day for the needs of your own household or farm. The exemption covers ordinary use of water and applies to the landowner. For a leasehold, a family allotment garden (ROD) or a business, ask Wody Polskie.
What is the penalty for not notifying a well?
Building a water installation without a required permit or notification carries an administrative fine, the amount of which depends on the case. An intake can be legalised, and for wells built before 18.08.2026 an amnesty applies if a complete application is filed by 31.12.2027.
How long does a water-law notification take?
You may start the works if, within 30 days of delivery of the notification, the authority has not raised an objection by decision. A request to supplement the notification suspends this period, and the authority may accept the notification earlier.
Sources
- Prawo wodne, consolidated text Dz.U. 2026 poz. 1335: Articles 33, 394, 395, 397, 421 - 424 (checked 16.11.2026)
- Wody Polskie: water-law notification, fee, deadlines and form (checked 16.11.2026)
- Prawo geologiczne i górnicze, consolidated text Dz.U. 2026 poz. 69: Article 3 point 2a
- Prawo budowlane, consolidated text Dz.U. 2026 poz. 524: Article 29 section 2 point 25
Planning a borehole and want to check which formalities apply to your plot? Write to us or call: +48 784 038 407. We will go through the depth, the purpose of the water abstraction and the order of the steps.
Further reading
- Article Deep well permit: when a water-law permit is needed in 2026
- Article A well for farming: how much water you need and the formalities in 2026
- Article Distance between a well and a septic tank or treatment plant: previous values and 2026 rules
- Guide Formalities: drilling a well and abstracting water