Acceptance of the well and installation

Acceptance should confirm the scope of the work done and the handover of the data for use. Treat acceptance of the borehole, installation of the equipment and assessment of the water quality separately.

Check the scope against the quote

Go through the items of the order: borehole, casing, screen, gravel pack, pumping, wellhead, pump, controls, trench and connection. For each item record done, not applicable or to be completed. Do not mark a gap as acceptance without reservations.

If the equipment is installed by a different company from the one that drilled the borehole, establish who is responsible for handing over the parameters and checking that the selection is compatible. A well-described division of scopes reduces later disputes.

Data for the well record

  • Location, date of completion, depth and diameters.
  • Borehole construction, the position of the screen section and the data supplied by the contractor.
  • Static and dynamic levels with the reference point.
  • Flow and duration of the pumping test, and observations.
  • Pump model, serial number and setting depth.
  • Control settings and equipment documents.

Have it demonstrated in practice

Ask for a demonstration of starting up, switching off and reading the alarms. Check with the contractor the water draw at the agreed points and the pressure during flow. Inspect the visible connections for leaks. Confirm how to switch the installation off safely and protect it for winter.

Electrical checks and protection tests are for a person with the proper qualifications. Do not run the pump dry or bypass alarms as part of a self-conducted acceptance.

Record reservations and next steps

In the acceptance report add the missing documents, defects, the person responsible and the agreed deadline for correction. Take photos of the visible components. Technical acceptance and clear-looking water do not replace testing its quality.

The ARCHE helper form organises your notes. It does not replace the contract, the contractor's documentation or the warranty document.

Sources:

Checked 8 October 2026

Read and plan further

Contact

Need help with your well?

Describe your needs or the symptoms. You can add the planner summary, test results and photos of the installation.

Other guides in this section

Free quote form

We call back within 24 hours

OFERTEO