50 m deep well

A 50-metre deep well is an ideal compromise between investment cost and hydraulic yield for owners of detached houses in Poland. According to the latest market data for 2026, the total cost of building a 50-metre well is PLN 19,100-22,475, and the investment pays for itself after 10-20 years on average, compared with the cost of drawing water from the municipal mains.

Compare information for other depths: 40 m well, 60 m well. The borehole depth is chosen to suit the conditions on the plot.

Studnia głębinowa 90m

How much does a 50 m deep well cost in 2026

Cost of a 50-metre borehole

At ARCHE, drilling a 50 m deep well costs PLN 14,000 net under the 2026 price list: PLN 9,000 for a borehole up to 30 metres plus PLN 250 for each additional metre (the rate depends on the diameter), i.e. PLN 9,000 + 20 × PLN 250.

The price covers drilling, installation of well pipes certified for drinking water, and pumping and cleaning the well. You do not pay for the casing, because we pull it out of the ground once the borehole is finished.

Cost of well equipment

A submersible pump suitable for a 50-metre well costs PLN 2,500-4,000, depending on hydraulic capacity and lift. For this depth you need a pump with a lift of at least 60-65 metres (50 m of depth + 10-15 m of working pressure + hydraulic losses in the pipeline).

A pressure tank (hydrophore) with a capacity of 100-150 litres costs PLN 750-1,400, a power cable with a cross-section of 4×2.5 mm and a length of 55 metres costs PLN 440-660, and a PE32 delivery pipe with a diameter of 32 mm and a length of 55 metres costs PLN 330-495. A wellhead with a cable gland costs PLN 280-420, and an electrical connection with protection devices costs PLN 800-1,500.

Total cost of a deep well

A complete 50-metre deep well with full hydraulic and electrical equipment costs PLN 19,100-22,475. The average price for typical geological conditions in Poland is PLN 20,800, including a submersible pump and all accessories.

Total drilling cost calculation:

ItemCost range
Borehole with casing and well screenPLN 14,000
Submersible pump with accessoriesPLN 2,500-4,000
Hydraulic and electrical equipmentPLN 2,600-4,475
Total costPLN 19,100-22,475
Studnia głębinowa 90m

50 m deep well

Why use our deep well drilling services?

Studnia Głębinowa Odwierty Śląsk

Top-quality water

The aquifer passes through several filtering layers, which cleans the water effectively.

Studnia głębinowa 90m

Lower costs

No more bills for the cubic metres of water you use.

Wiercenie Studni w Częstochowa

Installation safety

A guaranteed water supply tailored to your needs.

Financial viability of a 50 m deep well

Return on investment analysis for a 50-metre well

A 50 m deep well pays for itself after 10-20 years of use at an average water consumption of 150 cubic metres per year for a typical 4-person household. With higher water consumption (watering the garden, a swimming pool, a jacuzzi) the payback period becomes noticeably shorter.

Detailed profitability analysis of a 50 m deep well:

ItemCost / value
Initial cost of a 50 m wellPLN 20,800 (average)
Annual cost of mains waterPLN 1,800-2,400
Annual running cost of the wellPLN 400-750
Net annual savingsPLN 1,050-2,000
Payback period10-20 years

When is drilling a 50-metre well worthwhile?

A 50 m deep well is definitely a profitable investment in the following cases:

A 50-metre deep well is definitely a profitable investment where there is no access to the mains water network and the cost of a connection exceeds PLN 15,000, where water consumption is high (above 200 cubic metres per year), where intensive garden watering requires an additional 100-300 cubic metres per year, and where building a mains water connection is expensive because the plot is more than 100 metres from the network.

Investing in a 50 m well is also worth considering with average water consumption of 100-200 cubic metres per year, mains water access 50-100 metres from the plot, and planned higher water use because of building a swimming pool or extending the garden.

Cost comparison: 50-metre well vs municipal mains water for a detached house

50 m deep well versus municipal mains water. Detailed financial analysis over 10 years of use:

Comparison criterion50 m wellMunicipal mains water
Initial costPLN 20,800PLN 8,000-20,000*
Annual running costPLN 400-750PLN 2,000
Total 10-year costPLN 24,800-28,300PLN 28,000-40,000
Independence from the supplierFull autonomyNo independence
Water qualityNatural mineralisationChlorinated and fluoridated
Availability during outagesContinuousSupply interruptions

*the cost of a mains water connection depends on the distance to the network

costs well 50m vs mains

Technical specification of a 50 m well

Hydraulic and yield parameters

A 50 m deep well achieves a hydraulic yield of 1,500-4,000 litres per hour, depending on the local hydrogeological conditions of the site. The static water level is usually at a depth of 30-40 metres below ground level.

Detailed technical specification of a 50 m well:

  • The total depth of the borehole is 50 metres
  • Nominal borehole diameter: 150-200 millimetres
  • Casing diameter: PVC, 125 millimetres
  • Length of the screen section: 6-9 metres
  • Operating yield: 1.5-4.0 cubic metres per hour

Detailed pump parameters for the well

A 4-inch submersible pump with a capacity of 1.5-3.0 cubic metres per hour and a lift of 60-65 metres is the optimal solution for a 50-metre well. The electrical power of the pump should be 1.1-1.5 kilowatts at a supply voltage of 230 volts. The nominal diameter is 4 inches (100 millimetres), and the purchase cost is PLN 2,500-4,000.

Studnia Głębinowa

Free quote for a 50 m deep well

Fill in our deep well quote form, or contact us by email or phone.

Water quality from a 50 m deep well

Physical and chemical parameters of water from a depth of 50 m

Water drawn from a 50-metre well is of high microbiological quality thanks to natural filtration through successive geological layers. Total water hardness averages 10-16 degrees German hardness, and the pH is in the range 6.9-7.6.

Typical physical and chemical parameters of water from a 50 m well:

Parameter Value range Standard Status
Total hardness 10-16°dH no standard hard
pH 6.9-7.6 6.5-9.5 within the standard
Iron 1.5-6.0 mg/l 0.2 mg/l above the standard
Manganese 0.08-0.5 mg/l 0.05 mg/l above the standard
Pathogenic bacteria absent absent within the standard
Nitrates <10 mg/l 50 mg/l within the standard

Water treatment systems for a 50 m well

An iron and manganese removal system is the water treatment system most often required for water drawn from 50-metre wells. The cost of a complete system is PLN 4,000-8,500 for a capacity suited to supplying a household.

Ion-exchange water softeners that reduce water hardness are also available for PLN 3,200-6,000, as are UV disinfection lamps that eliminate bacteria and viruses for PLN 800-1,500.

Permits for a 50 m deep well

What permits are required to drill a well?

Under the Water Law Act (Prawo wodne) (Articles 33 and 395), constructing a water intake up to 30 m deep for ordinary water use and abstracting on average no more than 5 m³ per day for your own household or farm are exempt from a water-law permit and a water-law notification. A 50 m deep well is deeper than 30 m, so the applicable procedure must be checked with Wody Polskie before drilling.

These are separate conditions: one concerns constructing the intake, the other abstracting the water. A deeper borehole, or using water beyond ordinary use, requires checking the applicable procedure with Wody Polskie.

Formalities for a 50 m well

Because the borehole is deeper than 30 m, the applicable procedure and required documents must be checked with Wody Polskie before work starts. Siting requirements, source protection rules and geological regulations also apply, so before drilling we check the well location and the minimum distances listed below.

Minimum distances of a 50 m well from structures

Required distances of a 50-metre well from various structures on the plot in accordance with the Regulation of the Minister of Health on the quality of water intended for human consumption:

Structure / boundaryMinimum distance of the well
Boundary of the neighbouring plot5 m
Residential and farm buildings15 m
Liquid waste tanks30 m
Domestic wastewater treatment plants50 m
Sealed septic tanks and soakaway pits70 m

The well-building process step by step

Stage one: geological surveys and siting

Geophysical surveys using electrical resistivity tomography before drilling a well cost PLN 1,800-2,500 for a 400-metre profile and make it possible to determine the optimal well location and the expected hydraulic yield with 90-95 per cent accuracy. An alternative is an analysis of PIG (Polish Geological Institute) hydrogeological maps for PLN 300-600 or free observation of indicator vegetation.

Stage two: drilling the 50-metre borehole

Drilling a deep well takes 10-17 working hours in standard ground conditions in Poland. A truck-mounted drilling rig with 150-200 HP drills a borehole 150-200 millimetres in diameter at an average speed of 3-5 metres per hour.

The complete process includes preparing the drilling site in 1 hour, the drilling itself within 10-17 hours, installing the casing string over 2-3 hours, and cleaning the well with pumps, which takes 1-2 hours.

Stage three: installing the electrical equipment

Installing a submersible pump in a 50 m well requires a YKYY 4×2.5 mm cable 55 metres long (50 m of depth + 5 m of technical reserve). The pump is placed below the dynamic water level (the depth is set after the pumping test).

Installing the pump system includes installing the pump at the set depth, routing the power cables through a sealed wellhead, installing the pressure tank (hydrophore) in the building or in the water meter chamber, and connecting to the home water supply system.

Maintenance and running of a 50 m well

Inspection schedule for a 50-metre well

A technical inspection of a 50 m well should take place every 6 calendar months, covering a check of the water level, the pressure in the pressure tank (hydrophore) system and the electrical parameters of the pump. The annual cost of maintenance and minor repairs is PLN 200-400, including consumables.

Maintaining a 50 m well requires checking the water level and pump parameters every 6 months, disinfecting the well with chlorine once a year in line with PZH (National Institute of Public Health) standards, testing water quality in an accredited laboratory every 2 years, and replacing the submersible pump with a new one every 8-12 years.

Annual running costs of a 50-metre-deep well

Running a 50-metre well costs PLN 400-750 per year for a standard 4-person household using 150 cubic metres of water. The electricity consumption of the pump is 1.2-1.8 kilowatt-hours per cubic metre of water produced.

The annual running costs of a 50 m well consist of electricity for the pump at PLN 200-350 (150 m³ × PLN 1.3-2.3/m³), maintenance and technical inspections at PLN 150-250, and minor repairs and parts replacement at PLN 50-150, giving a total annual cost of PLN 400-750.

Wiercenie - Studnia Głębinowa Arche S.C.
Studnia Głębinowa

Book a well drilling date

We build deep wells in every type of ground! Deep well drilling has been our passion since 2019! Get in touch and find out the cost of building a deep well!

Comparison of a 50 m deep well with other depths

Comparison with other depths

DepthConstruction cost (borehole)Water-law permitYieldPayback
15 metresPLN 9,000Not required1,200-3,500 L/h7-13 years
30 metresPLN 9,000Not required1,500-4,000 L/h8-15 years
50 metresPLN 14,000To be checked with Wody Polskie1,500-4,000 L/h10-20 years

A 50 m deep well offers a good price-to-yield ratio.

Why drill to a depth of 50 metres?

A 50-metre borehole is worth considering because of its optimal hydraulic yield for households, access to stable, high-quality aquifers and moderate annual running costs. As it is deeper than 30 m, the applicable procedure must be checked with Wody Polskie before drilling.

Maintenance and running of a 50 m well

Inspection schedule for a 50-metre well

A technical inspection of a 50 m well should take place every 6 calendar months, covering a check of the water level, the pressure in the pressure tank (hydrophore) system and the electrical parameters of the pump. The annual cost of maintenance and minor repairs is PLN 200-400, including consumables.

Maintaining a 50 m well requires checking the water level and pump parameters every 6 months, disinfecting the well with chlorine once a year in line with PZH (National Institute of Public Health) standards, testing water quality in an accredited laboratory every 2 years, and replacing the submersible pump with a new one every 8-12 years.

Annual running costs of a 50-metre deep well

Running a 50 m well costs PLN 400-750 per year for a standard 4-person household using 150 cubic metres of water. The electricity consumption of the pump is 1.2-1.8 kilowatt-hours per cubic metre of water produced.

The annual running costs of a 50 m well consist of electricity for the pump at PLN 200-350 (150 m³ × PLN 1.3-2.3/m³), maintenance and technical inspections at PLN 150-250, and minor repairs and parts replacement at PLN 50-150, giving a total annual cost of PLN 400-750.

What does the well drilling price include?

The overall price for drilling a deep well is calculated according to the rate – per metre of borehole – and depends on the depth of the hole to be drilled.

The cost of such a well depends on several parameters. Remember that the cost may also vary with the location where the deep well drilling takes place.

When drilling a well, the price is affected by:

  • the depth of the drilled well
  • the diameter of the well casing
  • the type of slotted well screen

When installing and equipping the well, the price is affected by:

– the type of well enclosure
– the type of submersible pump
– the type of pumping set installation
– the size of the pressure tank (hydrophore)
– the type of wellhead
– the number of concrete rings
– the type of pump, pressure tank and pressure switch
– the length of the pipeline bringing water to the house
– the depth of the trench, the pressure line trench and the power supply

In most cases the company can only give a price for the service after talking to the customer. A borehole up to 30 metres costs PLN 9,000 net, and each additional metre PLN 250 net (depending on the diameter).

Keep in mind that the cost of drilling a well sometimes includes the cost of the casing. It is therefore worth checking whether this is the reason for an inflated price. A higher price should be justified: as we mentioned above, the reason is often simply the need to drill a wider hole or to use a more expensive drilling method because of the geological conditions.

Under the ARCHE price list, drilling a 50 m deep well costs PLN 14,000 net. On top of the borehole you need to budget for a submersible pump with fittings and its installation (PLN 700 net + materials under the ARCHE price list).

Service name (borehole):

Price from (net):

Deep well  110Φ

PLN 250 per metre *

Deep well  125Φ

PLN 250 per metre *

50 m deep well

Ikona Dom

Well for your home

Drilling a deep well is currently the best way to get free, clean water in your home.

Ikona Firma

Well for businesses

Wells for industry and commerce are a fairly popular solution, especially for car washes, swimming pools, thermal baths, spas and agritourism businesses.

Ikona Gospodarstwo

Well for agriculture

Industrial pumps that can move hundreds of metres of water per hour.

How do we drill a well?

Step by step to your deep well in Katowice

1 krok budowy studni głębinowej

1. Free quote

We discuss the borehole, the location and the way it will be carried out

2 krok budowy studni głębinowej

2. Choosing the pump

Choosing the pump and accessories

3 krok budowy studni głębinowej

3. Choosing the location

We decide where on your plot the water will be drawn

4 krok budowy studni głębinowej

4. Drilling the well

The well is drilled on the date you choose.

Book a date for drilling your well

We drill with specialist equipment, the Rotomax XL GT.
With us you get a guarantee of quality.

Reviews

See our projects

Find an answer

Answers to the questions our customers ask most often

 

A complete 50 m deep well costs PLN 19,100-22,475 (including drilling at PLN 14,000 net under the ARCHE price list), depending on the geological conditions of the site and the technical equipment chosen.

 

A 50 metre well is deeper than 30 m, so the applicable procedure must be checked with Wody Polskie before drilling. The exemption from a water-law permit and notification covers constructing an intake up to 30 m deep for ordinary water use.

 

A 4-inch submersible pump with a capacity of 1.5-3.0 cubic metres per hour and a lift of 60-65 metres of water column. The pump power should be 1.1-1.5 kilowatts. The purchase cost of a submersible pump is PLN 2,500-4,000.

 

A 50 m well pays for itself after 10-20 years of use at an average water consumption of 150 cubic metres per year. A household saves PLN 1,050-2,000 per year compared with the cost of mains water.

 

A 50 m deep well yields 1,500-4,000 litres per hour depending on local hydrogeological conditions. That equals 36-96 cubic metres per day: enough for any household.

 

Drilling a 50 m well takes 1-2 working days. The rotary drilling itself takes 10-17 hours, and complete installation with the electrical equipment takes 2-3 working days.

 

The water is drinkable but may need treatment. It often contains excess iron (1.5-6.0 mg/l against a standard of 0.2 mg/l) and is hard (10-16°dH). An iron removal system costs PLN 4,000-8,500.

 

The required minimum distances are 5 metres from the plot boundary, 15 metres from residential buildings, 30 metres from liquid waste tanks, and 50 metres from domestic wastewater treatment plants.

 

The annual running cost is PLN 400-750 and covers electricity for the pump (PLN 200-350), technical maintenance (PLN 150-250) and minor repairs (PLN 50-150).

 

Wells can be drilled all year round. In winter work can take slightly longer because of the frozen surface layer of the ground, but modern drilling equipment copes with difficult weather conditions.

 

Check the technical condition of the pump and the well screens. Flushing the well with pumps often helps.

 

The water is of high microbiological quality thanks to natural geological filtration. Typical parameters for the water are hardness of 10-16°dH, pH 6.9-7.6 and iron 1.5-6.0 mg/l. It usually requires an iron removal system.

How much does a deep well cost? Write to us or call

ARCHE S.C logo

Check out our YouTube channel and Facebook:

See the towns where we drill every day!

Free quote form

We call back within 24 hours

OFERTEO