Deep well 15m
A 15 metre deep well is a borehole reaching a depth of exactly 15 metres, as defined by the Polish Geological Institute (Państwowy Instytut Geologiczny) in its “Analysis of Poland’s groundwater resources” (2024). A 15 m deep well gives access to stable aquifers while keeping the legal formalities simple under the Water Law Act (Prawo wodne).
Compare the information for other depths: 20 m well. The depth of the borehole is chosen to suit the conditions on your plot.
- High-quality water from the depths
- Gain independence and never worry about running out of water
- Lower costs compared with mains water
How much does a 15 metre deep well cost in 2026
Cost of drilling to a depth of 15 metres
At ARCHE, drilling a 15 m deep well costs PLN 9,000 net under the 2026 price list (a fixed price for a borehole up to 30 metres). The price covers drilling, installation of well pipes certified for drinking water, and pumping and cleaning the well. You do not pay for the casing, because we pull it out of the ground once the borehole is finished.
Cost of well equipment
A submersible pump suitable for a 15 metre well costs PLN 1,200-2,800, depending on its hydraulic capacity and lift. For this depth you need a pump with a lift of at least 40-45 metres (15 m of depth + 10-15 m of working pressure + hydraulic losses in the pipework).
A pressure tank (hydrophore) with a capacity of 100-150 litres costs PLN 750-1,400, a 4×2.5 mm power cable 20 metres long PLN 160-240, and a PE32 rising main 32 mm in diameter and 20 metres long PLN 120-180. A wellhead with a cable gland costs PLN 280-420, and the electrical connection with protection devices PLN 800-1,500.
Total cost of a deep well
A complete 15 metre deep well with full hydraulic and electrical equipment costs PLN 12,310-15,540. The average price for typical geological conditions in Poland is PLN 13,900, including a submersible pump and all accessories.
Calculation of the total drilling costs:
| Item | Cost range |
|---|---|
| Borehole with casing and well screen | PLN 9,000 |
| Submersible pump with accessories | PLN 1,200-2,800 |
| Hydraulic and electrical equipment | PLN 2,110-3,740 |
| Total cost | PLN 12,310-15,540 |
15 m deep well
Why use our deep well drilling services?
Top-quality water
The aquifer passes through several filtering layers, which cleans the water effectively.
Lower costs
No more bills for the cubic metres of water you use.
Installation safety
A guaranteed water supply tailored to your needs.
Is a 15 m deep well financially worthwhile?
Return on investment analysis for a 15 m well
A 15 m deep well pays for itself after 7-13 years of use at an average water consumption of 150 cubic metres per year for a typical 4-person household. With higher water use (watering the garden, a swimming pool, a hot tub) the payback period becomes noticeably shorter.
Detailed profitability analysis of a 15 m well:
| Item | Cost / Value |
|---|---|
| Initial cost of a 15 m well | PLN 13,900 (on average) |
| Annual cost of mains water | PLN 1,800-2,400 |
| Annual running cost of the well | PLN 400-750 |
| Net annual savings | PLN 1,050-2,000 |
| Payback period | 7-13 years |
When is drilling a 15 metre well worthwhile?
A 15 m deep well is clearly a worthwhile investment in the following cases:
A 15 metre deep well is clearly a worthwhile investment where there is no access to the mains water network and the cost of a connection exceeds PLN 15,000, where water use is high (above 200 cubic metres per year), where intensive garden watering needs an extra 100-300 cubic metres per year, and where building a mains connection is expensive because the network is more than 100 metres away.
A 15 m well is also worth considering with an average water use of 100-200 cubic metres per year, with mains water available 50-100 metres from the plot, and with a planned increase in water use because of a swimming pool or a larger garden.
Cost comparison: 15 metre well vs municipal mains water for a detached house
A 15 m deep well versus municipal mains water. Detailed financial analysis over 10 years of use:
| Comparison criterion | 15 m well | Mains water |
|---|---|---|
| Initial cost | PLN 13,900 | PLN 8,000-20,000* |
| Annual running cost | PLN 400-750 | PLN 2,000 |
| Total 10-year cost | PLN 17,900-21,400 | PLN 28,000-40,000 |
| Independence from the supplier | Full autonomy | No independence |
| Water quality | Natural mineralisation | Chlorinated and fluoridated |
| Availability during outages | Continuous | Supply interruptions |
*the cost of a mains water connection depends on the distance to the network
Technical characteristics of a 15 m well
Hydraulic and yield parameters
A 15 m deep well reaches a hydraulic yield of 1,500-4,000 litres per hour, depending on the local hydrogeological conditions of the site. The static water level is usually at a depth of 8-15 metres below ground level.
Detailed technical characteristics of a 15 m well:
- Total depth of the borehole is 15 metres
- Nominal diameter of the borehole: 150-200 millimetres
- Casing diameter: PVC 125 millimetres
- Length of the screen section: 6-9 metres
- Operating yield: 1.5-4.0 cubic metres per hour
- Static water level: 8-15 metres below the surface
Detailed pump parameters for a 15 m well
A 4-inch submersible pump with a capacity of 1.5-3.0 cubic metres per hour and a lift of 45-50 metres is the optimal solution for a 15 metre well. The electrical power of the pump should be 1.1-1.5 kW at a supply voltage of 230 V. The nominal diameter is 4 inches (100 millimetres), and the purchase cost is PLN 1,200-2,800.
Free quote for a 15 m deep well
Fill in our deep well quote form, or contact us by email or phone.
Water quality from a 15 m deep well
Physical and chemical parameters of water from a depth of 15 m
Water drawn from a 15 metre well is of high microbiological quality thanks to natural filtration through successive geological layers. The total hardness of the water averages 10-16 degrees German hardness, and the pH is in the range 6.9-7.6.
Typical physical and chemical parameters of water from a 15 m well:
| Parameter | Range of values | Standard | Status |
|---|---|---|---|
| Total hardness | 10-16°dH | no standard | hard |
| pH | 6.9-7.6 | 6.5-9.5 | within the limit |
| Iron | 1.5-6.0 mg/l | 0.2 mg/l | above the limit |
| Manganese | 0.08-0.5 mg/l | 0.05 mg/l | above the limit |
| Pathogenic bacteria | absent | absent | within the limit |
| Nitrates | <10 mg/l | 50 mg/l | within the limit |
Water treatment systems for a 15 m well
An iron and manganese removal system is the treatment system most often required for water drawn from 15 metre wells. A complete system costs PLN 4,000-8,500 for a capacity suited to supplying a household.
Ion-exchange water softeners for PLN 3,200-6,000 are also available to reduce water hardness, as are UV disinfection lamps for PLN 800-1,500 that eliminate bacteria and viruses.
Permits for a 15 m deep well
Does a 15 m well need a water-law permit?
A 15 m deep well does not require a water-law permit or a water-law notification if it is used for ordinary water use. Under the Water Law Act (Prawo wodne) (Articles 33 and 395), constructing a water intake up to 30 m deep for ordinary water use and abstracting on average no more than 5 m³ per day for your own household or farm are exempt from a water-law permit and a water-law notification.
These are separate conditions: one concerns constructing the intake, the other abstracting the water. A deeper borehole, or using water beyond ordinary use, requires checking the applicable procedure with Wody Polskie.
Formalities for a 15 m well
For ordinary water use a 15 m well needs neither a water-law permit nor a water-law notification to Wody Polskie. However, the exemption does not lift siting requirements, source protection rules or geological regulations, so before drilling we check the well location and the minimum distances listed below.
Minimum distances of a 15 m well from other structures
The required distances of a 15 metre well from various structures on the plot, in line with the regulation of the Minister of Health on the quality of water intended for human consumption:
| Structure / boundary | Minimum distance from the well |
|---|---|
| Neighbouring plot boundary | 5 m |
| Residential and farm buildings | 15 m |
| Liquid waste tanks | 30 m |
| Domestic wastewater treatment plants | 50 m |
| Sealed septic tanks and soakaways | 70 m |
The well-building process step by step
Stage one: geological surveys and siting
Geophysical surveys using electrical resistivity tomography before building a 15 m well cost PLN 1,800-2,500 for a 400 metre profile and make it possible to determine the best location for the well and the expected hydraulic yield with 90-95 percent accuracy. The alternatives are an analysis of PIG hydrogeological maps for PLN 300-600, or free observation of indicator vegetation.
Stage two: drilling the 15 metre borehole
Drilling a 15 metre deep well takes 4-8 working hours in standard ground conditions in Poland. A truck-mounted drilling rig with 150-200 hp drills a borehole 150-200 millimetres in diameter at an average speed of 3-5 metres per hour.
The complete process includes setting up the drilling site in 1 hour, drilling the 15 metre borehole itself in 4-8 hours, installing the casing string in 2-3 hours, and cleaning the well with pumps, which takes 1-2 hours.
Stage three: installing the electrical equipment
Installing a submersible pump in a 15 m well requires a YKYY 4×2.5 mm cable 20 metres long (15 m of depth + 5 m of technical reserve). The pump is placed at a working depth of 11-14 metres below ground level.
Installing the pump system includes placing the pump at a depth of 11-14 metres, running the power cables through the sealed wellhead, installing the pressure tank (hydrophore) in the building or in a water meter chamber, and connecting it to the home plumbing system.
Maintenance and running of a 15 m well
Inspection schedule for a 15 metre well
A technical check of a 15 m well should be carried out every 6 calendar months and include checking the water level, the pressure in the pressure tank system and the electrical parameters of the pump. The annual cost of maintenance and minor repairs is PLN 200-400, including consumables.
Maintaining a 15 m well requires checking the water level and pump parameters every 6 months, disinfecting the well with chlorine once a year in line with PZH standards, analysing the water quality in an accredited laboratory every 2 years, and replacing the submersible pump with a new one every 8-12 years.
Annual running costs of a 15 metre deep well
Running a 15 metre well costs PLN 400-750 per year for a standard 4-person household using 150 cubic metres of water. The pump uses 1.2-1.8 kilowatt-hours of electricity per cubic metre of water produced.
The annual running costs of a 15 m well consist of electricity for the pump at PLN 200-350 (150 m³ × PLN 1.3-2.3/m³), maintenance and technical inspections at PLN 150-250, and minor repairs and replacement of parts at PLN 50-150, which gives a total annual cost of PLN 400-750.
Book a well drilling date
We build deep wells in every type of ground! Deep well drilling has been our passion since 2019! Get in touch and find out the cost of building a deep well!
Comparing a 15 m well with other depths
Comparison with other depths
| Depth | Construction cost (borehole) | Water-law permit | Yield | Return on investment |
|---|---|---|---|---|
| 15 metres | PLN 9,000 | Not required | 1,500-4,000 L/h | 7-13 years |
| 30 metres | PLN 9,000 | Not required | 1,500-4,000 L/h | 8-15 years |
| 35 metres | PLN 10,250 | To be checked with Wody Polskie | 1,800-4,500 L/h | 8-16 years |
A 15 metre deep well offers the best ratio of price to yield while still avoiding the need for a water-law permit.
Why choose a depth of 15 metres?
A deep well of exactly 15 metres is the best investment choice because the hydraulic yield is ideal for households, you get access to stable, high-quality aquifers, the annual running costs are moderate, and no water-law permit or notification is needed for ordinary water use.
Maintenance and running of a 15 m well
Inspection schedule for a 15 metre well
A technical check of a 15 m well should be carried out every 6 calendar months and include checking the water level, the pressure in the pressure tank system and the electrical parameters of the pump. The annual cost of maintenance and minor repairs is PLN 200-400, including consumables.
Maintaining a 15 m well requires checking the water level and pump parameters every 6 months, disinfecting the well with chlorine once a year in line with PZH standards, analysing the water quality in an accredited laboratory every 2 years, and replacing the submersible pump with a new one every 8-12 years.
Annual running costs of a 15 metre deep well
Running a 15 m well costs PLN 400-750 per year for a standard 4-person household using 150 cubic metres of water. The pump uses 1.2-1.8 kilowatt-hours of electricity per cubic metre of water produced.
The annual running costs of a 15 m well consist of electricity for the pump at PLN 200-350 (150 m³ × PLN 1.3-2.3/m³), maintenance and technical inspections at PLN 150-250, and minor repairs and replacement of parts at PLN 50-150, which gives a total annual cost of PLN 400-750.
What does the well drilling price include?
The overall price for drilling a deep well is calculated according to the rate – per metre of borehole – and depends on the depth of the hole to be drilled.
The cost of such a well depends on several parameters. Remember that the cost may also vary with the location where the deep well drilling takes place.
When drilling a well, the price is affected by:
- the depth of the drilled well
- the diameter of the well casing
- the type of slotted well screen
When installing and equipping the well, the price is affected by:
– the type of well enclosure
– the type of submersible pump
– the type of pumping set installation
– the size of the pressure tank (hydrophore)
– the type of wellhead
– the number of concrete rings
– the type of pump, pressure tank and pressure switch
– the length of the pipeline bringing water to the house
– the depth of the trench, the pressure line trench and the power supply
In most cases the company can only give a price for the service after talking to the customer. A borehole up to 30 metres costs PLN 9,000 net, and each additional metre PLN 250 net (depending on the diameter).
Please remember that the cost of drilling a well sometimes includes the cost of the pipes. It is therefore worth checking whether this is the reason for an inflated price. A higher price should be justified: as we mentioned above, the cause is often simply the need to drill a wider borehole or to use a more expensive drilling method because of the geological conditions.
Under the ARCHE price list, drilling a 15 m deep well costs PLN 9,000 net. On top of the borehole you need to budget for a submersible pump with fittings and its installation (PLN 700 net + materials under the ARCHE price list).
|
Service name (borehole): |
Price from (net): |
|
Deep well 110Φ |
PLN 250 per metre * |
|
Deep well 125Φ |
PLN 250 per metre * |
Deep well 15 metres

Well for your home
Drilling a deep well is currently the best way to get free, clean water in your home.

Well for businesses
Wells for industry and commerce are a fairly popular solution, especially for car washes, swimming pools, thermal baths, spas and agritourism businesses.

Well for agriculture
Industrial pumps that can move hundreds of metres of water per hour.
How do we drill a well?
Step by step to your deep well in Katowice

1. Free quote
We discuss the borehole, the location and the way it will be carried out

2. Choosing the pump
Choosing the pump and accessories

3. Choosing the location
We decide where on your plot the water will be drawn

4. Drilling the well
The well is drilled on the date you choose.
Book a date for drilling your well
We drill with specialist equipment, the Rotomax XL GT.
With us you get a guarantee of quality.
Reviews
Find an answer
Answers to the questions our customers ask most often
A complete 15 m deep well costs PLN 12,310-15,540 (including drilling at PLN 9,000 net under the ARCHE price list), depending on the geological conditions of the site and the technical equipment you choose.
A well exactly 15 metres deep does NOT require a water-law permit. Constructing an intake up to 30 m deep for ordinary water use and abstracting on average up to 5 m³ per day for your own household are exempt from a water-law permit and a water-law notification.
A 4-inch submersible pump with a capacity of 1.5-3.0 cubic metres per hour and a lift of 45-50 metres of water column. The pump power should be 1.1-1.5 kilowatts. The purchase cost of a submersible pump is PLN 1,200-2,800.
A 15 m well pays for itself after 7-13 years of use at an average water consumption of 150 cubic metres per year. A household saves PLN 1,050-2,000 per year compared with the cost of mains water.
A 15 m deep well yields 1,500-4,000 litres per hour depending on local hydrogeological conditions. That equals 36-96 cubic metres per day: enough for any household.
Drilling a 15 m well takes 1 working day. The rotary drilling itself takes 4-8 hours, and complete installation with the electrical equipment takes 1-2 working days.
The water is drinkable, but it may need treatment. It often contains too much iron (1.5-6.0 mg/l against a limit of 0.2 mg/l) and is hard (10-16°dH). An iron removal system costs PLN 4,000-8,500.
The required minimum distances are 5 metres from the plot boundary, 15 metres from residential buildings, 30 metres from liquid waste tanks and 50 metres from domestic wastewater treatment plants.
The annual running cost is PLN 400-750 and covers electricity for the pump (PLN 200-350), technical maintenance (PLN 150-250) and minor repairs (PLN 50-150).
A well can be drilled all year round. In winter the work may take slightly longer because of the frozen surface layer of the ground, but modern drilling equipment copes well with difficult weather conditions.
Check the technical condition of the pump and the well screens. Flushing the well with pumps often helps.
The water is of high microbiological quality thanks to natural geological filtration. Typical parameters for this water are hardness 10-16°dH, pH 6.9-7.6 and iron 1.5-6.0 mg/l. It usually needs an iron removal system.
How much does a deep well cost? Write to us or call
Drilling tips
Read the latest posts on our blog. Gather the knowledge you need before choosing the best option for you.