{"id":7813,"date":"2026-02-01T21:16:13","date_gmt":"2026-02-01T20:16:13","guid":{"rendered":"https:\/\/studniaglebinowa.eu\/deep-wells\/building-a-well-step-by-step\/"},"modified":"2026-11-16T22:10:42","modified_gmt":"2026-11-16T21:10:42","slug":"building-a-well-step-by-step","status":"publish","type":"post","link":"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/building-a-well-step-by-step\/","title":{"rendered":"Deep well construction step by step: stages, time and costs"},"content":{"rendered":"<p>Deep well construction takes place in seven stages: survey and choice of location, formalities, drilling, installing the casing with the screen and gravel pack, pumping test, installing the pump with the well-to-house connection, and water testing and handover. The drilling itself usually takes from a few hours to two days, but the whole process from the first conversation to water at the tap takes longer, because it includes formalities, groundworks for the connection and water testing. Legal position as at 16.11.2026.<\/p>\n<p>Drilling a well up to 30 m for ordinary use of water, and abstraction not exceeding an annual average of 5 m\u00b3 per day for the needs of your own household or farm, are exempt from a water-law permit and notification (Articles 33 and 395 of the <a href=\"https:\/\/api.sejm.gov.pl\/eli\/acts\/DU\/2026\/1335\" target=\"_blank\" rel=\"noopener\">Water Law Act (Prawo wodne)<\/a>, consolidated text, Dz.U. 2026 poz. 1335). These are separate conditions, one for drilling the well and one for abstracting water. A deeper borehole, or use of the water beyond ordinary use, requires checking the correct procedure with Wody Polskie. The exemption does not remove siting requirements, the protection of water intakes or geological regulations.<\/p>\n<h2>What a deep well is and what it looks like once built<\/h2>\n<p>A deep well is a vertical borehole drilled by machine down to an aquifer, lying at a depth that depends on the location and the geology. It differs from a dug well in that it draws water from layers isolated from surface contamination, so it usually protects water quality better. Hydrogeological maps that help assess where and how deep water occurs are provided by the <a href=\"https:\/\/www.pgi.gov.pl\/\" target=\"_blank\" rel=\"noopener\">Polish Geological Institute &#45; PIB<\/a>.<\/p>\n<p>Once construction is finished, there is little to see on the plot: a cover or enclosure with a wellhead, from which a rising main runs into the ground towards the house. Everything else is underground. In the borehole stands a well casing with a screen in the water-bearing zone, surrounded by a gravel pack, and the pump hangs below. The pump delivers water through a pipeline to a pressure tank, and a pressure switch or controller starts it when the pressure drops and stops it when the set value is reached. We explain how this system works in the article <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-how-it-works\/\">how a deep well works<\/a>, and we show a cross-section element by element in the <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-diagram\/\">deep well diagram<\/a>. For a general overview of the subject, from costs to regulations, see the guide on <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-cost-regulations-depth\/\">what a deep well is<\/a>.<\/p>\n<p>A deep well reaches layers lying much deeper than an Abyssinian well, which is a shallow driven well that uses water lying just below the surface. The yield and quality of water from the two solutions differ, so before choosing it is worth comparing them for your own plot rather than relying on general figures.<\/p>\n<h2>Deep well construction step by step: overview of the stages<\/h2>\n<p>The table below shows the order of the work, and under it we describe each stage separately. We give the time where it can be predicted. The other stages depend on the plot, the contractor&#8217;s schedule and the authorities.<\/p>\n<figure class=\"wp-block-table\">\n<table>\n<thead>\n<tr>\n<th>Stage<\/th>\n<th>What happens<\/th>\n<th>What is included in the cost<\/th>\n<th>Time<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td>1. Survey and location<\/td>\n<td>inspection of the plot, choice of location, access for equipment<\/td>\n<td>usually included in the borehole quote<\/td>\n<td>depends on dates<\/td>\n<\/tr>\n<tr>\n<td>2. Formalities<\/td>\n<td>checking permit exemptions, any notifications<\/td>\n<td>official fees only in unusual cases<\/td>\n<td>depends on the office<\/td>\n<\/tr>\n<tr>\n<td>3. Drilling<\/td>\n<td>borehole down to the aquifer<\/td>\n<td>metres of borehole<\/td>\n<td>a few hours to 2 days<\/td>\n<\/tr>\n<tr>\n<td>4. Casing, screen and gravel pack<\/td>\n<td>casing string, screen in the water-bearing zone, gravel pack<\/td>\n<td>casing, screen, gravel pack<\/td>\n<td>during drilling<\/td>\n<\/tr>\n<tr>\n<td>5. Pumping test<\/td>\n<td>checking the yield and the clarity of the water<\/td>\n<td>crew time and test pump<\/td>\n<td>depends on the well<\/td>\n<\/tr>\n<tr>\n<td>6. Pump and connection<\/td>\n<td>pump, rising main, cable, pressure tank, enclosure<\/td>\n<td>pump, pressure tank, pipe, cable, labour<\/td>\n<td>depends on the length of the route<\/td>\n<\/tr>\n<tr>\n<td>7. Water test and handover<\/td>\n<td>laboratory analysis, handover of the work<\/td>\n<td>test, any water treatment<\/td>\n<td>depends on the laboratory<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<\/figure>\n<figure class=\"wp-block-image size-full\"><img loading=\"lazy\" class=\"wp-image-5653\" src=\"https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa.jpg\" alt=\"A drilling rig with a tall mast standing on a lawn next to a house while a deep well is being drilled\" width=\"963\" height=\"957\" loading=\"lazy\" decoding=\"async\" title=\"\" srcset=\"https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa.jpg 963w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-300x298.jpg 300w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-150x150.jpg 150w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-768x763.jpg 768w\" sizes=\"auto, (max-width: 963px) 100vw, 963px\" \/><figcaption>A drilling rig set up on a lawn. Before the equipment arrives, it is worth agreeing the access route and a place for the spoil.<\/figcaption><\/figure>\n<h3>Stage 1. Survey and choosing the location<\/h3>\n<p>The first stage is deciding where to drill and how deep you can expect to find water. The survey relies on maps, records of neighbouring wells and the contractor&#8217;s experience in the area. No method guarantees finding water at a depth known in advance, and how reliable the results are depends on the geological conditions. That is why we price drilling per metre, and the price list has a separate rate per metre for a dry borehole, where no water was found.<\/p>\n<p>Three things matter when choosing the location: access for the drilling rig and the service vehicle, the distance to the building where the tank and controls will stand, and the distances from the plot boundary, the septic tank and farm buildings. The previous regulation on technical conditions ceased to apply in September 2026 and a new one has not yet been published, so we agree the distances from the boundary, the septic tank and buildings with the designer and the district office (starostwo), relying on previous practice and draft regulations. The values used until now, such as 5 m from the plot boundary, 15 m from sealed waste tanks and livestock buildings, or 30 m from a drain field for treated wastewater, are explained in a separate article on the <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/well-location-distances\/\">distance of a well from the plot boundary<\/a>.<\/p>\n<p>The depth you can expect depends on the geology. In sandy areas it can be shallower, in clay and rock areas deeper. There is no single minimum depth for a deep well, because what counts is whether the borehole reaches an aquifer that is well isolated from the surface and whether it yields enough water. A broader discussion of what the depth depends on is in the article on the <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-depth-requirements\/\">depth of a deep well<\/a>.<\/p>\n<h3>Stage 2. Formalities before drilling<\/h3>\n<p>The formalities depend on the depth, the amount of water abstracted and what the water will be used for. For a domestic well up to 30 m, from which abstraction does not exceed an annual average of 5 m\u00b3 per day, no water-law permit or notification is needed, as we explain at the beginning of this article. The same 30 m threshold comes from the Water Law Act, not from what is convenient for drilling.<\/p>\n<p>There are a few situations in which things get more complicated. When the water is to serve a business, relying on ordinary use of water is usually not enough, so the procedure has to be checked with Wody Polskie. Depending on the depth, the amount of water and the area, geological regulations may also apply, so there is no single rule for every well. The enclosure is treated separately from the water intake: building enclosures for groundwater intakes requires neither a building permit nor a notification (Article 29 section 2 point 25 of the Construction Law (Prawo budowlane)), but that does not mean all work around the well is exempt.<\/p>\n<p>A full description of the exemptions, exceptions and the order in which to deal with the matters is in the article on <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-permit-and-notification\/\">whether a deep well needs a permit<\/a>. If you are unsure whether your case falls within the exemption, ask Wody Polskie before the equipment arrives.<\/p>\n<h3>Stage 3. Drilling the deep well<\/h3>\n<p>Drilling is the shortest but most spectacular stage. A tracked drilling rig drives onto the plot and drills the borehole down to the aquifer. We drill by the percussion method, with a compressor, and the crew works on a Rotomax XL GT rig. The casing pipes that protect the borehole walls during the work are pulled out once it is finished. The details of the technology and the regulations covering the process itself are described in the article on what <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-drilling-stages-cost\/\">deep well drilling<\/a> looks like.<\/p>\n<p>A standard 30 m well is usually completed in one working day, and in harder ground and at greater depths drilling takes longer, up to two days. Drilling can be carried out all year round. The borehole itself is technically no different in winter than in summer, and if the ground is frozen the connection to the house can be finished in spring.<\/p>\n<figure class=\"wp-block-image size-full\"><img loading=\"lazy\" class=\"wp-image-5660\" src=\"https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-1024x536.jpg\" alt=\"An ARCHE tracked drilling rig on a plot during well drilling, with a green hose carrying away water and an excavator next to it\" width=\"1024\" height=\"536\" loading=\"lazy\" decoding=\"async\" title=\"\" srcset=\"https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-1024x536.jpg 1024w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-300x157.jpg 300w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-768x402.jpg 768w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-1536x804.jpg 1536w, https:\/\/studniaglebinowa.eu\/wp-content\/uploads\/2025\/09\/Studnia-Glebinowa-Budowa-2048x1072.jpg 2048w\" sizes=\"auto, (max-width: 1024px) 100vw, 1024px\" \/><figcaption>Drilling on a residential plot: the rig, the hose carrying water away from the borehole and an earthmoving machine.<\/figcaption><\/figure>\n<p>At this stage spoil and water from the borehole come to the surface, so it is worth showing the contractor where to direct it. The equipment leaves marks on the lawn, and once the work is finished the area is tidied, but the lawn is usually fully restored only after the trenches for the connection have been dug.<\/p>\n<h3>Stage 4. Installing the casing, screen and gravel pack<\/h3>\n<p>Once the planned depth is reached, a string of well casing is lowered into the borehole. We use PVC-U pipes with a diameter of 125 mm, and in sandy ground 110 mm with a thicker gravel pack. The pipes are joined in sections and the screen is installed in the water-bearing zone. Its length is matched to the thickness of the layer.<\/p>\n<p>The space between the pipe and the borehole wall is filled with a filter gravel pack, usually fine-grained gravel (in the range of 2 &#45; 4 mm). It acts as a natural filter and stabilises the structure, and in ground with fine, running sand its selection decides whether sand will get into the water. A well-made gravel pack is the main reason a well keeps delivering clear water years later.<\/p>\n<p>This stage also creates protection for the upper part of the borehole against surface water getting in. The seal, wellhead and enclosure are chosen to suit the pipe and the structure you plan to build over the well.<\/p>\n<h3>Stage 5. Pumping test<\/h3>\n<p>Before the well gets its permanent pump, we check how much water it actually yields and whether the water clears. A pumping test means running the pump at a set flow rate and observing how the water level in the borehole changes. On this basis the pump and a safe abstraction rate are selected, because the yield of a well cannot be read from its depth alone.<\/p>\n<p>There is no single minimum yield for a deep well. For a house, what counts is demand: how many people use the water, whether you water a garden and how many large appliances run at the same time. Only a comparison with the pumping test result shows whether the well will be enough. A constant flow throughout the year cannot be guaranteed, because it depends on the aquifer, the construction of the well and how it is used.<\/p>\n<h3>Stage 6. Pump, connection and commissioning<\/h3>\n<p>A submersible pump hung in the borehole delivers water through a pipe to the building. When selecting it, what matters is the yield of the well and the head, that is, the depth to which the pressure in the installation and the pipe losses are added. In houses, 3 &#45; 4 inch pumps are the most common, and their power and parameters are matched to the pumping test result. How the pump is installed, suspended and connected is described in the article on <a href=\"https:\/\/studniaglebinowa.eu\/studnia-glebinowa\/montaz-pompy-glebinowej\/\">installing a submersible pump<\/a>.<\/p>\n<p>The power cable is run together with the rising main so that it is protected from damage. A PE (polyethylene) rising main with a diameter of 32 &#45; 40 mm runs to the building below the frost line, so the trench is usually dug to a depth of 1.2 &#45; 1.5 m. In the building stands the pressure tank, which is installed in a room with a temperature above 5\u00b0C. In the ARCHE price list, installing the pump costs PLN 700 net plus materials, and a complete connection installation costs PLN 1,500 net plus materials.<\/p>\n<p>Commissioning includes flushing the installation and setting the pressure tank parameters. Only then does water appear in the house, but it is not yet known whether it is fit to drink.<\/p>\n<h3>Stage 7. Water test and handover<\/h3>\n<p>The last stage is testing the water in a laboratory and handing over the work. Colour, clarity and the absence of smell do not confirm that water is fit to drink, and neither does the depth of the borehole. The State Sanitary Inspectorate (Sanepid) recommends testing well water before first use and at least once a year, as well as after flooding or a failure. Testing a private well is therefore recommended, not mandatory.<\/p>\n<p>The result is assessed against the <a href=\"https:\/\/api.sejm.gov.pl\/eli\/acts\/DU\/2026\/748\" target=\"_blank\" rel=\"noopener\">Polish Minister of Health regulation of 22.05.2026<\/a> on the quality of water intended for human consumption (Dz.U. 2026 poz. 748). For drinking water the parametric value for nitrates is 50 mg\/l, and for E. coli and enterococci it is 0 in 100 ml. Water from deep wells often exceeds the indicator values for iron (200 \u00b5g\/l) and manganese (50 \u00b5g\/l). This does not mean a defect in how the well was made, only a need for water treatment matched to the test result: a filter, an iron filter, a water softener or a UV lamp.<\/p>\n<p>If you suspect contamination, use a safe source of water for drinking and preparing food. Boiling alone does not remove chemical contaminants.<\/p>\n<h2>Deep well depth: how many metres need to be drilled<\/h2>\n<p>The depth of a domestic well depends on how deep the aquifer lies at the given location, so there is no single typical figure. The minimum depth of a deep well does not come down to one number: what matters is that the borehole reaches an aquifer that is well isolated from the surface.<\/p>\n<p>As a rough guide, in sandy areas 20 &#45; 35 m is usually enough, in clay areas 35 &#45; 60 m, and in rock sometimes more than 80 m is needed. A higher groundwater level allows a shallower well, but it does not replace a survey. The 30 m limit has legal significance: down to that depth, if the other conditions are met, the permit exemption described above applies. The 30 m threshold applies to the depth of a well for ordinary use of water, not to what is convenient for drilling.<\/p>\n<h2>How much deep well construction costs<\/h2>\n<p>The cost of building a well consists of the borehole, the pump with fittings and the connection, plus water testing and any water treatment. We give ARCHE prices net. We compare detailed per-metre rates in the article on <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/well-drilling-cost-per-metre\/\">the price of well drilling per metre<\/a>, and we describe the full scope of the service on the page about <a href=\"https:\/\/studniaglebinowa.eu\/studnie-glebinowe\/odwiert-studni\/\">deep well drilling<\/a>.<\/p>\n<figure class=\"wp-block-table\">\n<table>\n<thead>\n<tr>\n<th>Item<\/th>\n<th>ARCHE net price<\/th>\n<\/tr>\n<\/thead>\n<tbody>\n<tr>\n<td>Borehole up to 30 m<\/td>\n<td>PLN 9,000<\/td>\n<\/tr>\n<tr>\n<td>Each additional metre<\/td>\n<td>PLN 250<\/td>\n<\/tr>\n<tr>\n<td>Dry borehole (no water)<\/td>\n<td>PLN 150 per metre<\/td>\n<\/tr>\n<tr>\n<td>Pump installation<\/td>\n<td>PLN 700 + materials<\/td>\n<\/tr>\n<tr>\n<td>Complete connection installation<\/td>\n<td>PLN 1,500 + materials<\/td>\n<\/tr>\n<tr>\n<td>Taking and testing a water sample<\/td>\n<td>from PLN 1,200<\/td>\n<\/tr>\n<\/tbody>\n<\/table>\n<\/figure>\n<p>For a 30 m well, the ARCHE price list items alone give PLN 9,000 for the borehole, PLN 700 for pump installation and PLN 1,500 for the connection, that is PLN 11,200 net. On top of that come materials: the pump, pressure tank, rising main, cable and enclosure. Their prices depend on the class of equipment and the length of the route, so check them in a quote rather than in averaged tables.<\/p>\n<p>Running costs are small compared with construction. A typical domestic pump uses roughly 0.3 &#45; 0.6 kWh per m\u00b3 of water. At an electricity price of around PLN 1.0 &#45; 1.3 per kWh gross, depending on the tariff and the operator (indicative prices, checked on 16.11.2026), that comes to a few dozen groszy per m\u00b3. For four people using about 150 m\u00b3 a year, that is a few dozen zlotys a year for energy, more with intensive garden watering.<\/p>\n<h3>How to read the costs given<\/h3>\n<p>The ARCHE amounts given come from the price list and are net amounts. The scope of work and materials is set for a specific plot, so when comparing offers always establish the full amount payable and what it includes. Take into account energy, water testing, servicing, water treatment and a reserve for replacing equipment. Having your own well does not remove charges for wastewater discharged into the sewer.<\/p>\n<h2>What comes after construction: inspections and servicing<\/h2>\n<p>After handover the well needs periodic checks. It is worth checking the pump every few months: the electrical parameters, the water level in the well and the pressure in the installation. The pump usually needs replacing after more than a dozen years of normal operation. The annual cost of servicing depends on the scope of inspections and minor repairs.<\/p>\n<p>Disinfection is chosen to suit the construction of the well, the test results and the instructions of a product approved for the given use. Do not use toilet cleaners, perfumed bleaches or random swimming-pool chemicals. The dose and contact time are set on the basis of the actual volume of water and the installation conditions. In a drilled well it is difficult to distribute the product, so it is worth commissioning a specialist service. After flushing, a water test confirms the effect, because smell alone is not enough.<\/p>\n<h2>Is building your own well worth it<\/h2>\n<p>The payback time depends on consumption and local tariffs. A well replaces the water charge, but if the house is connected to the sewer, you still pay for wastewater. A well pays back fastest when it is used to water a garden, and with household use alone the payback takes noticeably longer. You will find an example comparison in the article <a href=\"https:\/\/studniaglebinowa.eu\/en\/deep-wells\/deep-well-vs-mains-water\/\">deep well or mains water<\/a>.<\/p>\n<p>Your own water source gives independence from rises in municipal water prices and from supply restrictions during network failures. However, the water quality has to be checked by testing, because the depth of the borehole does not guarantee it. With a well-built well, its lifespan is counted in decades, as long as the pump and enclosure are serviced.<\/p>\n<p>Want to check what these stages look like on your plot and how much the borehole will cost? <a href=\"https:\/\/studniaglebinowa.eu\/en\/contact-a-well-expert\/\">Contact an ARCHE expert<\/a>: we call back within 24 hours and work in Lesser Poland and Silesia.<\/p>\n<h2>Frequently asked questions<\/h2>\n<h3>How much does deep well construction cost?<\/h3>\n<p>A borehole up to 30 m costs PLN 9,000 net in the ARCHE price list, and each additional metre PLN 250 net. On top of that come pump installation (PLN 700 net plus materials), the connection (PLN 1,500 net plus materials) and the equipment itself. The total cost depends on the depth, the ground and the class of pump.<\/p>\n<h3>Does building a deep well require a permit?<\/h3>\n<p>Not always. Drilling a well up to 30 m for ordinary use of water and abstraction of up to an annual average of 5 m\u00b3 per day for the needs of your own farm are exempt from a water-law permit and notification. A deeper borehole or other use of water requires checking the procedure with Wody Polskie.<\/p>\n<h3>What are the components of a deep well?<\/h3>\n<p>A well casing with a screen in the water-bearing zone, a filter gravel pack, a submersible pump, a rising main with a cable, a wellhead or enclosure, and a pressure tank with controls in the building. We describe each element on the diagram in a separate article.<\/p>\n<h3>How do you know at what depth the water is?<\/h3>\n<p>From hydrogeological maps, data on neighbouring wells and the contractor&#8217;s experience in the area. Certainty comes only from the borehole and the pumping test, because no method gives the depth with a guarantee.<\/p>\n<h3>How long does deep well construction take?<\/h3>\n<p>The drilling itself takes from a few hours to 2 days, depending on the depth and the ground. The whole construction takes longer, because drilling is followed by pump installation, the trench for the connection and water testing.<\/p>\n<h3>Can you drill a well in winter?<\/h3>\n<p>Yes, drilling can be done all year round. The borehole itself is technically no different in winter than in summer, and if the ground is frozen the connection to the house is often finished only in spring.<\/p>\n<h2>Sources<\/h2>\n<ul>\n<li><a href=\"https:\/\/api.sejm.gov.pl\/eli\/acts\/DU\/2026\/1335\" target=\"_blank\" rel=\"noopener\">Prawo wodne, consolidated text, Dz.U. 2026 poz. 1335<\/a> &#45; the act, Articles 33 and 395 on ordinary use of water and permit exemptions (notice of 17.09.2026, status: in force).<\/li>\n<li><a href=\"https:\/\/api.sejm.gov.pl\/eli\/acts\/DU\/2026\/748\" target=\"_blank\" rel=\"noopener\">Rozporz\u0105dzenie Ministra Zdrowia z 22.05.2026, Dz.U. 2026 poz. 748<\/a> &#45; parametric and indicator values for the quality of water intended for consumption.<\/li>\n<li><a href=\"https:\/\/www.gov.pl\/web\/wody-polskie\/legalizacja-urzadzenia-wodnego\" target=\"_blank\" rel=\"noopener\">Wody Polskie: legalizacja urz\u0105dzenia wodnego<\/a> &#45; the procedure for wells built without the required consent.<\/li>\n<li><a href=\"https:\/\/www.pgi.gov.pl\/\" target=\"_blank\" rel=\"noopener\">Polish Geological Institute &#45; PIB<\/a> &#45; hydrogeological maps and data.<\/li>\n<\/ul>\n\n\n<div class=\"kk-star-ratings kksr-auto kksr-align-center kksr-valign-bottom\"\n    data-payload='{&quot;align&quot;:&quot;center&quot;,&quot;id&quot;:&quot;7813&quot;,&quot;slug&quot;:&quot;default&quot;,&quot;valign&quot;:&quot;bottom&quot;,&quot;ignore&quot;:&quot;&quot;,&quot;reference&quot;:&quot;auto&quot;,&quot;class&quot;:&quot;&quot;,&quot;count&quot;:&quot;0&quot;,&quot;legendonly&quot;:&quot;&quot;,&quot;readonly&quot;:&quot;&quot;,&quot;score&quot;:&quot;0&quot;,&quot;starsonly&quot;:&quot;&quot;,&quot;best&quot;:&quot;5&quot;,&quot;gap&quot;:&quot;5&quot;,&quot;greet&quot;:&quot;&quot;,&quot;legend&quot;:&quot;0\\\/5 - (0 votes)&quot;,&quot;size&quot;:&quot;0&quot;,&quot;title&quot;:&quot;Deep well construction step by step: stages, time and costs&quot;,&quot;width&quot;:&quot;0&quot;,&quot;_legend&quot;:&quot;{score}\\\/{best} - ({count} {votes})&quot;,&quot;font_factor&quot;:&quot;1.25&quot;}'>\n            \n<div class=\"kksr-stars\">\n    \n<div class=\"kksr-stars-inactive\">\n            <div class=\"kksr-star\" data-star=\"1\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" data-star=\"2\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" data-star=\"3\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" data-star=\"4\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" data-star=\"5\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n    <\/div>\n    \n<div class=\"kksr-stars-active\" style=\"width: 0px;\">\n            <div class=\"kksr-star\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n            <div class=\"kksr-star\" style=\"padding-right: 5px\">\n            \n\n<div class=\"kksr-icon\" style=\"width: 0px; height: 0px;\"><\/div>\n        <\/div>\n    <\/div>\n<\/div>\n                \n\n<div class=\"kksr-legend\" style=\"font-size: 0px;\">\n            <span class=\"kksr-muted\"><\/span>\n    <\/div>\n    <\/div>\n","protected":false},"excerpt":{"rendered":"<p>Deep well construction step by step: 7 stages from choosing the site to handover, with timing and costs. Legal position and ARCHE prices as at 16.11.2026.<\/p>\n","protected":false},"author":5,"featured_media":10206,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"footnotes":""},"categories":[149],"tags":[],"class_list":["post-7813","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-deep-wells"],"_links":{"self":[{"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/posts\/7813","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/users\/5"}],"replies":[{"embeddable":true,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/comments?post=7813"}],"version-history":[{"count":11,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/posts\/7813\/revisions"}],"predecessor-version":[{"id":10511,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/posts\/7813\/revisions\/10511"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/media\/10206"}],"wp:attachment":[{"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/media?parent=7813"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/categories?post=7813"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/studniaglebinowa.eu\/en\/wp-json\/wp\/v2\/tags?post=7813"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}